Following an important update to NSW fire safety regulations for external wall cladding, ARA Building successfully removed and replaced non-compliant cladding for two residential buildings in Sydney’s CBD.

From January to August 2018, the ARA Building carried out the complete re-cladding of two residential towers near King St Wharf in Sydney’s CBD.

New fire safety regulations

At the bid of the building’s insurer, ARA Building fired a sample of the original cladding and for testing

While undertaking a separate remedial project at the property, it was suspected that the cladding on 23 Shelley Street and 35 Shelley Street might be combustible. 

At the request of the building’s insurer, ARA Building removed a sample of the original cladding and sent it for testing, which confirmed that it did not comply with the NSW Government’s new fire safety regulations.

Installation of the new frame structure

In response to the findings, ARA Building’s Project Manager, Dusko Dragicevic, worked closely with Bill Moisidis, the Director of Bellmont Façade Engineering, to determine the best materials for the complete re-cladding of 23 Shelley Street (14 storeys) and 35 Shelley Street (10 storeys).

After removing the original non-compliant cladding and framing for both façades, the ARA Building Team carried out the installation of the new frame structure, new non-combustible sarking from TBA Firefly, and approximately 1,500+m2 of Fairview Architectural’s deemed non-combustible aluminum panels, the Vitracore G2 in Silver Ice Metallic.

Scaffolding & CBD Location

ARA Building provided scaffolding across the façades of both buildings, requiring various council

ARA Building provided scaffolding across the façades of both buildings, requiring various council and road authority permits. This was especially complex given the location in Sydney’s CBD.

However, the team’s experience with obtaining all relevant permits meant that they were able to avoid unexpected variations in quoting for the permits.

Vitracore G2 Deemed Non-Combustible Aluminum Panels

The Vitracore G2 is the first brand that has been able to reach the new Australian fire safety rating. With large stock holdings and short lead times, the Vitracore G2 proved to be a cost-effective solution that is visually similar to traditional Aluminum Composite Panels (ACP), but with a deemed non-combustible core. “We take a lot of care to deliver an outstanding product to the client” – Dusko Dragicevic, Project Manager, ARA Building.

The Vitracore G2 panels are lighter and more delicate than traditional ACP, which made the installation process safer and faster for the ARA Building team. It also meant that the team had to take special care to protect the panels from any damage that might occur during installation. Overall, the client was pleased with the final delivery of the cladding.

TBA Firefly Non-Combustible Sarking

ARA Building installed TBA Firefly’s Non-Combustible Sarking across both façades

Firefly’s non-breathable, non-combustible sarking is an extra heavy-duty radiant barrier designed to be used as a water/vapor/reflective insulation barrier in commercial wall applications that require non-combustible materials.

ARA Building installed TBA Firefly’s Non-Combustible Sarking across both façades to enhance the level of fire safety protection for the external wall cladding in the event of a fire.

Inspection & Compliance

ARA Building is an expert in carrying out inspections for external façade fire safety on high-rise buildings (Class 2 to 9 buildings – Type A & B Construction) and making any updates in order to comply with the current code.

Meeting the current requirements is one of the most important aspects in keeping any building and its occupants safe and limiting the spread of fire via the external wall and between adjacent buildings. If they have any enquiries about the cladding on the building, please contact ARA Building.

Download PDF version Download PDF version

In case you missed it

Siemens Expands Fire Safety With Danfoss Acquisition
Siemens Expands Fire Safety With Danfoss Acquisition

Siemens Smart Infrastructure has completed the acquisition of Danfoss Fire Safety, a Denmark-based specialist in fire suppression technology. This strategic step will boost growth...

Specification And Installation: The Key To Effective Door Controls
Specification And Installation: The Key To Effective Door Controls

Safe and seamless movement in our built environment hinges on accurately specified and installed door hardware, explains Russell Marks, managing director of Boss Door Controls. Wi...

AEI Cables: Fire Safety And Building Compliance
AEI Cables: Fire Safety And Building Compliance

Many of the new requirements under the new Building Safety Act 2022 are still not understood by those making critical decisions in the fire safety supply chain, says cable supplier...

vfd