The Federal Emergency Management Agency (FEMA) allocated over $786 million to the Puerto Rico Electric Power Authority (PREPA) to replace nearly 1.5 million meters damaged by Hurricane María.

These will have Advanced Metering Infrastructure (AMI), a two-way communications technology that collects detailed metering information for all of PREPA’s service areas. 

situational awareness

AMI will improve the operation of the electric system, as well as the metrics and situational awareness of the Authority and customers to address security issues and irregular situations during future atmospheric events.

The smart meters will also allow real-time reading so that customers can be aware of voltage quality.

greater transparency

The funds are part of the allocations under FEMA’s Accelerated Awards Strategy (FAASt) for the Authority"

The funds are part of the allocations under FEMA’s Accelerated Awards Strategy (FAASt) for the Authority. These meters will provide greater transparency to customers about the service they receive,” said Federal Disaster Recovery Coordinator José G. Baquero.

"The infrastructure will also help the government meet its energy public policy goals, according to federal and local statutes."

smart meters

The FEMA-approved project establishes that there will be a better detection of energy service interruptions, as well as a more accurate estimate of outage periods for affected customers.

In addition, the smart meters will provide information to identify faults with hot sockets or fallen wires, for example, to dispatch assistance equipment, if necessary.

AMI technology

Interconnection points can be provided for a better distribution of resources and thus reduce interruptions

Furthermore, AMI technology will facilitate the integration of microgrid networks to restore power using alternate energy resources.

By identifying service capacity in challenging areas, interconnection points can be provided for a better distribution of resources and thus reduce interruptions created by energy demand.

FEMA donations

To date, FEMA has allocated nearly $31.6 billion for nearly 10,900 projects to address Puerto Rico's recovery from Hurricane María. In September 2020, FEMA obligated nearly $9.5 billion to PREPA through the FAASt program for the repair of its energy infrastructure.

To date, FEMA has awarded over $1.2 billion for about 1,100 permanent construction projects in private, nonprofit facilities throughout Puerto Rico, including long-term care facilities and nursing homes.

Download PDF version Download PDF version

In case you missed it

The Technologies Of Smart Cities: Their Impact On The Fire Service
The Technologies Of Smart Cities: Their Impact On The Fire Service

To be a smart city, modern urban areas leverage technology to improve operations and services, in effect deploying a network of sensors and devices to collect data on city operatio...

Is Outdated Technology Crippling The Fire Safety And Security Sector?
Is Outdated Technology Crippling The Fire Safety And Security Sector?

In the challenging world of fire safety and security services, organizations are constantly juggling the need to maintain high efficiency with the relentless push for technological...

Rosenbauer Karlsruhe: New Welcome Center In Germany
Rosenbauer Karlsruhe: New Welcome Center In Germany

The new Welcome Center of Rosenbauer Karlsruhe in Germany can already be seen from far away in the city and from the busy highway that runs through Karlsruhe. At night, the strikin...

vfd